Valar
Nuclear Construction Tools
A suite of procurement, estimating, and contractor management tools built for the Ward 250 HTGR pilot plant at the Utah San Rafael Energy Lab in Orangeville, Utah — developed as part of research for a Director of Contracts & Procurement role at Valar Atomics.
Ward 250 — Contractor Register
Covers 12 WBS construction phases. Two tabs: Utah local contractors and national firms with nuclear/DOE credentials. Includes prequalification tracking, RFQ status, bid received, and contract award fields with dropdown validation. 60+ real firms sourced for each trade scope.
Download Contractor Register (.xlsx)
Ward 250 — Construction Procurement Tool
Master procurement and subcontractor management workbook. Eight tabs: Dashboard with live KPIs, Contractor Register, Bid Leveling (6-bidder comparison), Procurement Tracker, Change Order Log, Risk Register, Prequalification Log, and RACI Matrix.
Download Procurement Tool (.xlsx)
Ward 250 — HTGR Cost Estimate
AACE Class 3 bottom-up cost estimate for a 100–250 kWt TRISO-fueled HTGR pilot plant. 90+ line items across 12 WBS sections. Benchmarked against NGNP, HTTR, Project Pele, and INL meta-analysis data. Summary, WBS detail, Assumptions, and Benchmark tabs.
Download Cost Estimate (.xlsx)
Built using publicly available data on Valar Atomics, DOE Reactor Pilot Program, INL advanced reactor cost studies, and Utah construction market data. Estimate accuracy: AACE Class 3 (−20% / +30%).